|
ENGITECT
Issue
Three - Summer 1998
Introduction
Welcome to the third edition
of Engitect, Hurst, Peirce and Malcolm’s newsletter. Our aim
is to keep in touch with our clients and friends in the construction
sphere and to build on relationships which in some cases extend
back to the 1920’s.
We were pleased to find
that our photograph in the CDM section of the previous edition
showing the Greek painter working precariously at height prompted
many of you to write to suggest appropriate captions. More about
this later.
We hope you will find this
edition interesting and informative.
The
House of Lords
In 1995 we were commissioned
to provide structural engineering advice for the refurbishment
of the main roof over the House of Lords and Royal Gallery at
the Palace of Westminster. The brief was subsequently extended
to include an adjoining roof and also the introduction of supplementary
timber framing and support work to the ornate ceiling over the
Royal Gallery.
The House of Lords was built
as part of the Palace of Westminster redevelopment designed
by Charles Barry, between 1845 and 1850 and was a major engineering
structure of its time. Trusses with cast iron compression members
and wrought iron tension members span 46 ft. over the chambers.
The trusses support a lower ornate timber ceiling and an upper
fireproof ceiling of tile creasing arches.
The roof covering comprises
cast iron pan tiles measuring 800 x 800mm bolted to wrought
iron rafters which are supported on cast iron purlins spanning
between the trusses. One of the original truss drawings is reproduced
below. This was the first use of cast iron tiles for roof tiling
in this country. The idea was imported from France. To afford
better corrosion protection the tiles were galvanized. However,
after a few years the galvanizing started to break down and
rust patches appeared. As a consequence the tiles were painted
and the painting has been repeated from time to time ever since.
After 150 years it was time to give the tiles a major overhaul.
Otherwise, apart from a few fractures to lugs on the cast iron
purlins, and leaking, a matter about which Members were less
than happy, the roof has performed well.

The roof also suffered a direct
hit from a bomb during the second world war but fortunately
with only slight damage.
A pilot study had been carried
out by others to assess the feasibility of the roof refurbishment,
including the removal of the cast iron tiles for re-galvanising,
and with repairs to fractured elements and fittings. One concern
was that the extreme thermal range of 70 degrees Celsius to
which the tiles are subject was straining the roof and causing
fractures to lugs at the end connections of the cast iron purlins.
We arranged for the thermal range and relative movement between
the roof elements to be monitored during a very hot period and
were able to show that with minor modifications to the tile
fixings there was sufficient slackness in the roof to accommodate
the movement.
Removal of the roof tiles meant
that the trusses lost their lateral stability. Rather than introduce
an unwieldy system of temporary bracing we were able to devise
methods of stiffening the existing cast iron purlins to allow
them to act as props.
To keep out the weather, the
whole roof was encapsulated in a scaffold enclosure rising some
30m above ground level. The scaffold was portalised and with
a minimum of ties to the main structure was a major engineering
structure in itself. It required detailed interactive analysis
of the scaffold frame by the scaffold designer to satisfy us
that neither the scaffold nor the ties to the structure would
be overloaded under high wind conditions. The roof works are
complete with the repairs to the Royal Gallery ceiling due for
completion late this year.
It is slow because the working
hours are restricted to the times when the Lords are not sitting
and the Lords sit for more days per year than the Commons.
Back
to Top
The
Stent Shuffle
Question:
"How many items of plant can one safely operate on a site
measuring 12m x 24m?"
Answer:
"Quite a few actually."
The question arose when one
of our clients decided to proceed with works associated with
a hotel development in Knightsbridge. The development is to
comprise a luxury hotel with around 200 bedrooms.
The full site is ‘L’ shaped
in plan measuring a maximum of 40m x 30m. Five basement levels
will be required to accommodate support and ‘back of house’
facilities making it one of the deepest basements in central
London.
The perimeter wall is to be
formed with secant piles, the construction of which is described
in the panel. Even though only part of the site had been cleared
and an existing occupied building covers the majority of the
area, an opportunity was identified which would hasten the development
phase of the project.
Research led us to believe
that it was feasible to bore five secant piles across the entrance
to the area that had already been partially cleared. Installation
of these piles would release this area as the site entrance.
Thus, a works package comprising the demolition of a 12 metre
free standing wall restrained by flying shoring and the installation
of 5 secant and 2 ‘dummy’ piles was prepared and tenders were
sought.
The ‘dummy’ pile bores are
filled with sand so that the wall can be continued under the
next phase of work.
The work had to be carried
out to a strict 2 month timetable during November and December
of last year.
Griffiths McGee were appointed
to carry out the demolition work and Stent Foundations the piling
work with Bovis Construction as construction manager and Arup
Project Management overseeing contractual matters.

As you can see from the photograph
the site was extremely cramped when the Casagrande C50hydraulic
rotary piling rig complete with oscillator was delivered to
join the service crane, and mechanical excavator, together with
associated plant equipment and not forgetting, of course, the
ready mixed concrete truck. However, with careful site management,
progress from delivery of the piling rig during the night of
26th November 1997 to its removal on 18th
December 1997 was rapid.
The depth of secant cut is
in excess of 28 metres which we believe is as deep as has been
successfully achieved. Systematic checks on the vertical alignment
of the piles using an optical plummet/inverted plumb-bob and
total station showed that the accuracy exceeded expectations
Back
to Top
Secant
Pile Walls
Secant walls are
formed by concrete piles which have a positive interlock
with adjacent piles. The sequence of construction
is for primary (female) piles to be installed at a
spacing to allow intermediate (male) piles to be cut
into the female piles. Normally a thick wall casing
is oscillated through the female concrete which is
of a suitably low early strength, in order that it
can be cut. The female piles may be reinforced as
well as the males and thus can be used for high lateral
loads. The use of casing oscillators ensures a high
degree of positional and vertical control and the
system is ideal for irregular plan shapes.
|
CDM
and All That
You may recall the article
from our last Newsletter which included a photograph of a decorator
perched extremely precariously at eaves level on a two storey
Greek Villa on the Isle of Chios. A number of readers suggested
a caption for the painters colleague standing at ground level
in the foreground of the picture.
They included the following:
"'Hey, Zorba, you
‘ave meezzed a bit.'’
‘Stop complaining – Michaelangelo
didn’t have all that scaffolding when he was painting the ceiling.'
'Zorba, whatever you
do, don’t stand back and admire your handiwork.'"
However, by a unanimous decision
of the judging panel Michael Ney’s submission of:
"Man in foreground
- 'Oi, Spiros, why don’t you put that board horizontal.'
Reply- ‘You forget, Yanis,
it’s easier like this now my right leg's 50mm shorter since
the last accident!’"
was adjudged to be most appropriate.
Michael is awarded a bottle of champagne and many thanks to
all those who took the time and trouble to reply.
Perhaps you would like to put
your mind to the next caption competition. This lion was photographed
recently in New York. Suggestions please for what Barry Pitcher
is saying to his wife who is taking the photograph.

Answers
on a postcard please addressed to the editor. The winning entry
will receive a bottle of champagne
Back
to Top
New
Department Stores for JLP
HPM are assisting the John
Lewis Partnership with the fitting out of two brand new department
stores. One forms a major anchor tenancy on the £700m Bluewater
development near Dartford / Ebbsfleet in Kent and the new store
in Glasgow is the largest unit in the brand new Buchanan centre
at the eastern end of Glasgow’s main shopping thoroughfare,
Sauchiehall Street.
The 30,000m² (300,000 sq. ft.)
Bluewater store is laid out to trade from 3 levels with stock
holding and support facilities in a basement that extends the
full width of the retail areas above. The Glasgow store is slightly
smaller in terms of overall floor area and will trade from 4
floors reflecting the limitations of the more constricted city
centre site. As might be expected, both stores have extensive
mechanical and electrical plant, many of which are high quality
factory assembled modular units. The largest of these is the
generator mounted on the roof at Glasgow, which weighs about
14 tonnes. Part of our involvement has been to ensure that these
units can be lifted and supported at the desired location on
each building.
The development teams include
John Lewis architects, H & V and electrical engineers with
Brooker Flynn Architects providing assistance on Bluewater and
Legge Ericsson Architects at Glasgow. Davis Langdon and Everest
are quantity surveyors to both projects. Both stores are due
to open in early 1999.
Back
to Top
Partnership
News
We would like to welcome two
new members to our technical staff, Peter Bucher and David Hall.
Peter brings the skills he learnt when working in a District
Surveyor’s office to bear on our review work for the Grosvenor
Estates and other projects where we assess tenants work on behalf
of major property owners. David has joined our CAD staff to
keep pace with our expanding workload
Back
to Top
And Finally...
Continuing our series of
articles from the 19th Century on building practices
and hazards to health here is one to make the Planning Supervisor
go very pale! The article is taken from a book by T. Pridgin
Teale, M.A., surgeon to the General Infirmary at Leeds, published
in 1879, entitled Dangers to Health.
Arsenical Wall Papers.
T. Pridgin Teale records that
incidences of ill health after sleeping in newly wall-papered
rooms were common in the mid-19th Century. Research
concluded that almost all colours used in paper staining during
this period contained arsenic. So beware all those who are involved
in the refurbishment of properties from this period where multi-layers
of wallpaper are discovered!

Readers will note that 19th
Century decorators were unusually small men, or perhaps the
rooms were particularly lofty!
|